Doel 3 - Tihange 2 / German RSK Evaluation & Reply
[9] Annex to the letter from the Federal Ministry for the Environment, Nature Conservation, Building and Nuclear Safety (BMUB) of 28 August 2017 “Information for FANC and Belgian experts for the preparation of an expert meeting on the RPV issue Doel-3/Tihange-2”
[10]
Doel 3, Reactor Pressure Vessel, Safety Case Report Electrabel, Brussels, 05.12.2012
[11]
Tihange 2, Reactor Pressure Vessel, Safety Case Report Electrabel, Brussels, 05.12.2012
[12]
Doel 3, Reactor Pressure Vessel, Safety Case Report 2015 Electrabel, Brussels, 28.10.2015
[13]
Tihange 2, Reactor Pressure Vessel, Safety Case Report 2015 Electrabel, Brussels, 28.10.2015
[14]
Doel 3, Reactor Pressure Vessel, Safety Case Report Addendum Electrabel, Brussels, 26.04.2013
[15]
Tihange 2, Reactor Pressure Vessel, Safety Case Report Addendum Electrabel, Brussels, 15.04.2013
[16]
Indications de défauts dans les cuves des réacteurs de Doel 3 et Tihange 2 Chronologie et contexte scientifique du dossier https://afcn.fgov.be/fr/dossiers-dinformation/centrales-nucleaires-en- belgique/actualite/indications-de-defauts-dans-les
[17]
Examen des cuves PWR, Doel 3 VP-2016, Rapport de synthèse Rapport Areva DI 33943, Rev. 0, 06.12.2016
[18] Flaw indications in the reactor pressure vessels of Doel 3 and Tihange 2 Final Evaluation Report 2015 FANC-AFCN, 12.11.2015
RSK/ESK Secretariat at the Federal Office for the Safety of Nuclear Waste Management
Page 18 of 19